Holes #1, #3, #16, #18 complete with green or tee boxes left to shape
Hole #2 work in progress with pond under construction
Holes #4, #14 completed
Hole #15 tee boxes done with huge irrigation pond (5 acres) 2 weeks to completion
Holes #17 & #19 along with East side # 5 -#13 not started yet
Progress on Subdivision
Lots are being staked – road design completed with water & sewer engineering in progress
We have a target date of LOT SALES for October – we are waiting finalization of annexation and completion of Disclosure.